| The Eskom Coal Haulage Road Repair Programme |
 |
| Evaluation of strategic coal haulage routes between the coal mines and the Eskom power stations and the provision of engineering services and construction monitoring to repair, upgrade or reconstruct the respective routes. |
| Client: |
ESKOM |
Partners (in consortium): |
NETGroup, S.E.F., TGC, Lahmeyer International |
| Contract Period: |
5 years |
| Project Value: |
R2 billion |
| Telesure Headquarter |

|
| All civil and structural engineering services for a prestigious 55 000 square-metre office development for Telesure Investment Holdings in Johannesburg, South Africa. |
| Client: |
Steyn City Developments |
| Contract Period: |
2 years |
| Project Value: |
R410 million |
| The Oliver Tambo International Pier Project |
 |
| Civil and structural design, detailing and construction monitoring of Oliver Tambo International Pier Building. |
| Client: |
Oliver Tambo International Airport |
| Contract Period: |
3 years |
| Project Value: |
R550 million |
| North South Carrier 2 Water Transfer Project : Botswana |
 |
| Develop an integrated water balance and translate the various demands along the NSC corridor into a sustainable technical solution to enhance water supply to urban, rural and industrial developments within eastern Botswana. This includes conceptual design of NSC-1 refurbishments, conceptual design of NSC-2 transfer scheme, construction supervision and environmental reviews, audits and inspections. |
| Client: |
Government of Botswana |
| Contract Period: |
6 years |
| Project Value: |
R5 billion |
| Roodeplaat Temba Water Supply Project |
 |
| Client: |
Roodeplaat Temba Water Supply Scheme |
| Contract Period: |
6 years |
| Project Value: |
R700 million |
| Olievenhoutbosch Ministerial Housing Project Read More |
 |
| Access to basic infrastructure such as accommodation, water and sanitation through detailed engineering designs, construction monitoring and supervision, planning, organising, managing, controlling and coordinating the project’s activities. |
| Client: |
Absa Property Development |
| Contract Period: |
3 years |
| Project Value: |
R450 million |
| Thorntree View Human Settlement Read More |
 |
| Thorntree View is an embodiment of the Breaking New Ground principles at work. Its design stimulates wealth creation, poverty alleviation and equity by seamlessly blending 29 000 subsidised, institutional and bonded housing units with public open spaces, business and commercial stands, schools, sports fields and parks. |
| Client: |
Safdev SSDC |
| Contract Period: |
15 years |
| Project Value: |
R240 million |
| Nelspruit Water Treatment Works |

|
| The Mbombela Local Municipality commissioned the bulk-water and sewerage infrastructure project of R172 million to serve the Mbombela Stadium and the Mataffin precinct area in Nelspruit, South Africa. Bigen Africa is responsible for the consulting engineering, construction monitoring and quality assurance of the project. |
| Client: |
Mbombela Local Municipality |
| Contract Period: |
2 yrs |
| Project Value: |
R56 million |
| MINING: Joint Water Forum |
In June 2004, representatives of the Steelpoort Valley Producers Forum and the Mogalakwena Economic Sector Forum constituted a third forum called the Joint Water Forum. Its role was to specifically focus on water and the possible partnership with the Department of Water Affairs (DWA). In essence the JWF would act as both a stakeholder and a contributor. To date 28 mines are members of the forum. On 26 May 2008, DWA, JWF and Trans Caledon Tunnel Authority (DWA’s implementing agent) signed a Memorandum of Agreement, cementing collaboration among them on the implementation of the ORWRDP scheme, securing economic development, job creation and skills development in the area. |
| Client: |
A host of various mining companies including Veremo Holdings, Pietersburg Iron Ore, Modikwa Platinum, Umnotho weSizwe Group |
| Contract Period: |
Ongoing |
| Project Value: |
R10 million |
| Steelpoort Valley Producers Forum |
| The establishment of the Steelpoort Joint Development Forum, during 2002, between the Sekhukhune District Municipality and its five local municipalities of Greater Marble Hall, Greater Groblersdal, Greater Tubatse, Makhudutamaga and Fetakgomo, together with various mining companies in the Eastern Limb Mining Area illustrates that co-operative governance, in terms of the Constitution of the Republic of South Africa, can be successfully implemented, not only between the various spheres of government and organs of state, but also between the various spheres of government and the private sector. The Steelpoort Valley Producers Forum was established to attend to matters of mutual concern of mining companies in the Eastern Limb and to promote and encourage social and economic development in the area. |
| Client: |
A host of mining companies, including Bokoni Platinum Mine, Twickenham Platinum Mine, Marula Platinum Mine and Xstrata. |
| Contract Period: |
Ongoing |
| Project Value: |
R22 million |
|